Project Schedule
The project schedule will be updated as the PER is developed.
Town of Geraldine Project Implementation Schedule | |
Action | Date |
Public Hearing on Draft PER & EA | March 2022 |
Draft PER Complete | March 2022 |
Town Resolutions, PER adoption | April 2022 |
Prepare Final PER | May 2022 |
Apply for DNRC and MCEP Grants | May 2022 |
Apply for CDBG and RD Grant Funding | Fall 2022 |
DNRC and MCEP Awards | May 2023 |
Finalize Grant Financing and Startup | July 2023 |
Begin Design | August 2023 |
Design Basis Report/Cost Estimates to the Town of Geraldine | September 2023 |
Submit Design Plans and Specifications to MDEQ | September 2023 |
MDEQ Review & Approval | November 2023 |
Advertise for Bids | December 2023 |
Start Construction | March 2024 |
Complete Construction | October 2024 |