Project Schedule

The project schedule will be updated as the PER is developed.

Town of Geraldine Project Implementation Schedule
Action Date
Public Hearing on Draft PER & EA March 2022
Draft PER Complete March 2022
Town Resolutions, PER adoption April 2022
Prepare Final PER May 2022
Apply for DNRC and MCEP Grants May 2022
Apply for CDBG and RD Grant Funding Fall 2022
DNRC and MCEP Awards May 2023
Finalize Grant Financing and Startup July 2023
Begin Design August 2023
Design Basis Report/Cost Estimates to the Town of Geraldine September 2023
Submit Design Plans and Specifications to MDEQ September 2023
MDEQ Review & Approval November 2023
Advertise for Bids December 2023
Start Construction March 2024
Complete Construction October 2024