Project Schedule
The project schedule will be updated as the PER is developed.
| Town of Geraldine Project Implementation Schedule | |
| Action | Date |
| Public Hearing on Draft PER & EA | March 2022 |
| Draft PER Complete | March 2022 |
| Town Resolutions, PER adoption | April 2022 |
| Prepare Final PER | May 2022 |
| Apply for DNRC and MCEP Grants | May 2022 |
| Apply for CDBG and RD Grant Funding | Fall 2022 |
| DNRC and MCEP Awards | May 2023 |
| Finalize Grant Financing and Startup | July 2023 |
| Begin Design | August 2023 |
| Design Basis Report/Cost Estimates to the Town of Geraldine | September 2023 |
| Submit Design Plans and Specifications to MDEQ | September 2023 |
| MDEQ Review & Approval | November 2023 |
| Advertise for Bids | December 2023 |
| Start Construction | March 2024 |
| Complete Construction | October 2024 |